Dentons Kazakhstan
In 2026, the SpaceCon team delivered a comprehensive fit-out project for the new Dentons Kazakhstan office located in Almaty, at 110E Al-Farabi Avenue.
The project became a clear example of precise coordination between design, engineering, and construction under tight deadlines and elevated requirements for quality, safety, and representative office standards.
Project Overview
  • Total area: 1,415 m²
  • Location: Almaty, 110E Al-Farabi Ave.
  • SpaceCon’s role: Design development, engineering documentation, and general contractor
  • Project duration: 6 months
Design & Planning
The project began with a contract for the development of a comprehensive design concept and full set of working drawings, including architectural and engineering solutions.
Within a short timeframe, the SpaceCon team completed the design development, coordination, and issuance of the full project documentation, allowing construction to commence without delays.
A separate scope included the facade concept and design solutions, ensuring a cohesive architectural image and full alignment with the status of an international law firm.
General Contracting & Demolition
In August, the general contracting agreement was signed, and SpaceCon proceeded to the active construction phase.
At the initial stage, a full demolition was carried out:
  • complete removal of existing finishes,
  • dismantling of all engineering systems,
  • preparation of the site down to the concrete shell for the new build-out.
Engineering Systems & Construction
The key challenge of the project was the simultaneous coordination of multiple parallel processes, including:
  • complete replacement of the building façade;
  • installation of new engineering systems:
  • heating,
  • power supply,
  • ventilation and air conditioning,
  • fire protection piping,
  • water supply and drainage,
  • low-current systems,
  • structured cabling system (SCS);
  • full scope of interior finishing works.
All stages were executed in parallel according to a clearly structured schedule, allowing the overall project timeline to be significantly reduced without compromising quality.
Quality Control & Materials
Throughout construction, all technological processes and approved design solutions were strictly followed.
Thanks to the detailed project documentation, works progressed smoothly without on-site redesigns or downtime.
From the first days of construction, imported finishing materials and equipment were ordered, preventing supply delays and maintaining a high construction pace.
Project Completion
By the end of December, SpaceCon completed the main scope of works, which allowed in January 2026 to:
  1. begin furniture delivery;
  2. organize the relocation of the Dentons team;
  3. commission the office ahead of contractual deadlines.
Project Outcome
  • A modern, international-standard office
  • Full compliance with approved design and client standards
  • High levels of comfort, safety, and functionality
  • Strict adherence to deadlines and contractual obligations
  • Full end-to-end responsibility by SpaceCon
For us, it is essential not only to complete the works, but to provide the Client with confidence, comfort, and security at every stage of the project.
We are proud of the completed Dentons Kazakhstan office and the level of trust placed in our team.